When to Order Custom Villa Furniture from Foshan: A 6-Month Renovation, Floor-Plan Freeze & 30-Day Storage Timeline

Nanhai ~60,000㎡ Factory・4 In-House Lines | Longjiang 10,000㎡ Showroom・Video Inspection | 1-Set MOQ・30-Day Free Storage | FOB / CIF Export
The biggest scheduling bottleneck in villa renovations is rarely construction itself—it is ordering too late so move-in stalls, or finishing furniture too early and letting dust and moisture damage it on an unfinished site.
For overseas self-built villas, production, marble slab selection, inspection, and customs clearance must align smoothly.
Founded in Foshan in 2015, BRANUO pairs our ~60,000㎡ Nanhai factory with our ~10,000㎡ Longjiang showroom, offering 1-set MOQ and 30 days of free storage from the agreed delivery date. Follow this backward timeline to prevent scheduling mismatches.
1. Quick Answer: When Should You Lock Your Order?
- Domestic Villas & Penthouses: Confirm dimensions and schedule production 3–4 months before move-in, once carpentry framing and door-casing subframes are complete.
- Overseas Villas & Sea-Freight Projects: Account for ocean transit and destination customs by locking your design and deposit 5–6 months before move-in.
2. The 6-Month Backward Timeline (Domestic vs. Overseas Projects)
A backward schedule from floor-plan freeze and deposit to inspection and storage.
Swipe to view all 5 milestones →
- 015–6 Months Out
- Site stage
- MEP rough-in & subfloor/wall prep
- Action
- Finalize living, dining & bedroom layouts; measure elevator doors, cabin diagonals & stair turns
- BRANUO
- Confirm Sofa, Upholstered Bed & Marble Table models and split structures
- 024–5 Months Out
- Site stage
- Wall plastering / carpentry framing & stone walling
- Action
- Select leather, fabric, veneer & marble slabs; pay 50% deposit to start production
- BRANUO
- 45 days standard; 60 days custom dimensions; 60–90 days complex whole-home orders (excl. transit)
- 032.5–3 Months Out
- Site stage
- Cabinetry installation & paint/grout finishing
- Action
- Pre-shipment inspection (allow 3–5 cm handcrafted upholstery tolerance)
- BRANUO
- HD photo/video inspection, factory visit, or third-party SGS / BV inspection
- 041.5–2 Months Out
- Site stage
- Pre-deep-clean / awaiting final site handover
- Action
- Settle 50% balance to dispatch, or hold finished goods if site access is delayed
- BRANUO
- Dispatch within 3–5 business days; 30 days free storage included
- 050–1 Month Out
- Site stage
- Deep clean & HVAC commissioning complete
- Action
- Uncrating, on-site modular assembly & fine placement
- BRANUO
- Optional domestic door-to-door delivery & installation; overseas orders receive remote installation guidance and spare-parts support (quoted separately)

3. Three Scheduling Details Most Homeowners Overlook
1. Lock Dimensions & Access Clearances Before Waiting for Final Paint
Waiting until wall painting and wood paneling finish wastes one to two months. Once door casings, feature-wall thickness, and HVAC access panels are fixed, outer dimensions for wide-screen beds, curved sectionals, and dining tables can be locked immediately.
Measure elevator doors, cabin depth, and stair turns up front so our factory engineers split-module construction before sampling.
2. Buffer Time for Natural Marble Slab Selection
If your order includes natural marble dining or coffee tables, BRANUO selects slabs under unified quality control and sends real-scene photos or videos for grain approval before cutting.
Stone lead times depend on slab confirmation (about 45 days), so early approval keeps the entire shipment on track.
(Note: Every natural marble slab has unique veining; the physical slab governs.)
3. Use 30 Days Free Storage If Site Handover Slips

Minor construction delays are common. Once finished goods pass inspection, BRANUO provides 30 days of free storage from the agreed delivery date (standard storage rates apply thereafter). Keeping leather, upholstery, and stone inside our clean warehouse protects them from job-site dust and humidity.
4. Payment, Export Terms & Showroom Visits

- Payment & Dispatch: 50% deposit upon signing to enter production; 50% balance after inspection approval, with dispatch arranged within 3–5 business days of full payment receipt.
- Export & Delivery: Factory quotes exclude tax, freight, and installation. Overseas orders ship under FOB (Shenzhen / Guangzhou / Yantian) or CIF terms; our partner logistics network can arrange domestic door-to-door delivery and installation; overseas orders receive remote installation guidance and spare-parts support, with on-site installation not included (quoted separately by destination and floor access). Core markets include the USA, Canada, Australia, Singapore, Thailand, Malaysia, Cambodia, UAE, Saudi Arabia, India and Russia, plus Hong Kong & Macau and Taiwan.
- Showroom & Factory Tour: Schedule a visit to our ~10,000㎡ Longjiang showroom (No. 52, National Highway 325, Longjiang Town, Shunde District, Foshan), ~15 minutes from our Nanhai factory, to test comfort and inspect materials in person.
5. Frequently Asked Questions (FAQ)
Q1: Does this timeline apply if I only order a living room sofa or a master bed?
Yes. BRANUO supports 1-set MOQ, and single-piece custom orders follow the exact same 50% deposit, HD video/third-party inspection, and 30-day free storage policy.
Q2: How much transit time should overseas buyers add for Australia, the US, or Dubai?
Beyond the 45–90 day production window, reserve 30–45 days for ocean freight and port clearance depending on your destination, and verify local elevator or stairwell access before dispatch.
Q3: What warranty covers bespoke loose furniture and soft furnishings?
BRANUO provides a tiered warranty: Lifetime on solid-wood frames, 5 years on foam and hardware, 3 years on upholstery, and 1 year on finished goods and power-function mechanisms.
(Footer: Compliance & IP Disclaimer: Timelines listed are for project planning reference; exact production and delivery dates are governed by your signed order contract.
BRANUO fulfills custom orders based on client-provided original specifications in strict compliance with applicable design-patent and intellectual-property regulations.)